Summary
The committee is starting to scope out the Riverwalk South Extension and Hillside Gateway projects, which will shape how the Riverwalk extends south and how people enter the area. The discussion covers what the projects should include and what they might cost before any construction decisions are made.
At a glance
- Total mentions
- 6
- Last 30 days
- 2
Rising — discussed at 3 meetings since Sep 21, 2026, up from 2 in the two months before.
Impact analysis
Project costs are on the table but no figures have been shared yet.
Residents and visitors who use the Riverwalk and its southern gateways.
Taxpayers bear the cost if private fundraising falls short.
Mentions & discussions (5)
Riverwalk Planning, Design and Construction Committee — November 2, 2026
The committee is starting to scope out the Riverwalk South Extension and Hillside Gateway projects, which will shape how the Riverwalk extends south and how people enter the area. The discussion covers what the projects should include and what they might cost before any construction decisions are made.
City Council — October 27, 2026
A resident challenged the $6.8 million River Walk South extension in the budget, calling it a want, not a need, and noting taxpayers haven't met fundraising goals.
City Council — September 21, 2026
The Riverwalk Commission is pushing for $6.8 million to fund the South Extension and Hillside Gateway project. Council members and former commissioners discussed rising project costs, private donations, and project scope.
Riverwalk Commission — August 12, 2026
The new North Central College Riverwalk Park is under active construction, with completion expected October 30, 2026. Grade beams and low-flow walk piers are going in now.
Riverwalk Planning, Design and Construction Committee — August 4, 2026
Two competing visions for the riverbank near Eagle Street: a naturalized shoreline with native plants (Option A) versus a wider 8-foot concrete walk (Option B). Design isn't budgeted until 2029 and construction until 2031, with updated concepts due in early 2027.
Related development
Eagle Street South Bank Improvements
This stretch of riverbank will eventually get either more green, natural shoreline or a wider, more accessible walkway — but not until construction in 2031.
NCC Riverwalk Park
A new park segment on the Riverwalk serving the college and the public, with a slight delay possible from flood repairs.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Naperville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.