A change order adds about $120,000 and 61 days to the Fire Station 4 renovation project, bringing the total to about $3 million.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Last discussed Jun 2, 2026.
Impact analysis
Adds up to $120,145, bringing the project total to $3,018,145.
Fire crews and the neighborhoods they serve get a modernized station.
Mentions & discussions (2)
City Council — November 4, 2026
A change order adds about $120,000 and 61 days to the Fire Station 4 renovation project, bringing the total to about $3 million.
City Council — June 2, 2026
The council approved major infrastructure investments including over $5 million for local street resurfacing and nearly $2.9 million for improvements at Fire Station #4.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Naperville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.